White Chapel Primary School
Works were completed in the boiler room at the school and consisted of the cut-out and removal of pipework and the removal of the Asbestos residue on the walls.
In addition, we undertook to remove all of the paint for the boiler room walls using a Blast & Breathe Removal System. This was completed to ensure that any risk of Asbestos being present under the painted walls was eliminated.
- Client: Bowker Ltd
- Contract Period: 10 days
- Contract Type: Removal of Asbestos Residue and Abrasive Blasting
- Value: £8,900